作为承包商的任何支付的先例,招揽机构可以要求承包商提交任何的完整的弃权说明书和和任何人员、机构或者劳务公司、服务、有关设备或者材料的公司的所有索赔豁免材料,或者任何有关与施工有关的材料。按照要求,承包商也必须提供所有这样索赔已经满意的可接受证据。
另外,所有支付承包商的金额,招揽机构可以在下列情况下予以扣留,如果:
A. 任何招揽机构对承包商正式提出索赔没有受理, 或者,如果招揽机构要求按照所在国的法律法规,通过沙特阿拉伯政府扣留这些金额;或者
B. 承包商在缺少这份合同的任何条件或者条款时;或者
C. 有合理的怀疑这份合同在规定时间内完成,如果承包商是,或者合同价格的余额未付,或者承包商没有按照合同条款履行义务时。
如果招揽机构不满意上述扣留的原因,必须立即支付扣留金额。如果上述扣留的原因在对承包商的书面通知之后,没有迅速解除,招揽机构要求承包商支付纠正的开支,并且扣除因此造成的所有费用和花费,或者可能将到期的开支。如果扣留的部分,在本合同条款规定下,不足以支付这样的费用,或者在最后的款项支付之后发生,承包商和它的保证人或者保证人,如果有,必须迅速支付因此招致任何费用给招揽机构,出现这样的索赔或者,索赔可以强加给一个永久施工项目的留置权或者房地产、永久施工项目或者任何属于皇室委员会其它财产。
P-4 资金的转让
按照本合同规定,承包商不得分配到期的资金, 或者未经招揽机构书面许可,承包商的银行除外。 如果招揽机构,同意这样的资金转让,在支付到期前至少10数天,书面通知招揽机构。
任何资金的分派以招揽机构适当的抵销利益为准,并扣除本合同所有的扣留金额。
P-3 RELEASES AND WITHHELD AMOUNTS
As a condition precedent to making any payments to the Contractor, the Soliciting Agency may require Contractor to submit complete waivers and releases of any and all claims of any person, firm or corporation supplying labor, services, equipment or materials in connection with, or in any way related to, the performance of the Work. Upon request, the Contractor shall also furnish acceptable evidence that all such claims have been satisfied.
In addition, any amounts otherwise payable to the Contractor hereunder may be withheld, in whole or in part, by the Soliciting Agency if:
A. Any claims are filed against Contractor by Soliciting Agency, or if Soliciting Agency is required to withhold such amounts by the Government of Saudi Arabia pursuant to the laws and regulations of the Kingdom; or
B. Contractor is in default of any of the terms or conditions of this Contract; or
C. There is reasonable doubt that this Contract can be completed within the time specified, or for the balance of the Contract Price then unpaid, or if the Contractor is otherwise in default of its obligations under the Contract.
If the foregoing causes for withholding are removed to the satisfaction of Soliciting Agency, the withheld payments will be paid promptly. If such causes are not promptly removed after written notice to Contractor, the Soliciting Agency may rectify the same at Contractor's expense and deduct all costs and expenses incurred thereby from such withheld payments or from any other monies due, or which may become due, to Contractor. If the amount of such withheld payments or other monies due Contractor under this Contract is insufficient to meet such costs, or if any claim against Contractor is discharged by Soliciting Agency after final payment is made, the Contractor and its guarantors or sureties, if any, shall promptly pay Soliciting Agency all costs incurred thereby regardless of when such claim arose or whether such claim imposed a lien upon the Permanent Works or the real property upon which the Permanent Works are situated or any other property belonging to the Royal Commission.
P-4 ASSIGNMENT OF MONIES
Contractor shall not assign monies due, or to become due, to it under this Contract except to the Contractor's Bank without the prior written consent of Soliciting Agency. In the event that Soliciting Agency consents to such assignment of monies, written notice thereof shall be given to Soliciting Agency at least ten (10) days before payment is due.
Any assignment of monies shall be subject to all proper set-offs in favor of Soliciting Agency and to all deductions and withholdings provided for in this Contract.
P-5 NOT USED
2014.10.17