标书蓄冰设备调试目的翻译-中英对照
1. The purpose for ice storage equipment debugging
①. 通过调试,检验蓄冰设备安装和运行工况是否符合设计要求和设计目的;
②. 保障设备能够运行良好,保障北京华彬国际大厦酒店工程供冷功能的实现;
③. 培训业主方操作人员,使其掌握设备的使用和维护;
(1)Through testing, check whether the installation and operation operating mode of the ice storage equipment is complied with the designing requirement and purpose of design;
(2).Ensure the sound operation of equipment, ensure the realization of the cooling function of Beijing Hua Bin International hotel in China;
(3)Train the operating personnel of the owner; make it understand the operation and maintenance of the equipment;
2、 蓄冰设备调试内容
2. Content of ice storage equipment test
①. 检测每项蓄冰设备与各个系统的运行工况。
Check the operating modes of every ice storage device and every system
②. 配合机电总包及冷冻机组厂家等单位检测蓄冰设备与整个系统的运行有关的控制系统的运作。
Support electromechanical general address contractors and refrigeration unit manufacturers etc. to check the operation of control systems concerning ice storage devices and the whole system
③. 配合机电总包及冷冻机组厂家等单位汇编所有提交的数据及操作与维修指导。
Support electromechanical general address contractors and refrigeration unit manufacturers etc. to compile all the submitted data and instructions of operation and maintenance
④. 汇编所有的设备安装检测记录和验收报告。
Compile all the installment and checking records and acceptance reports
3、 蓄冰设备调试准备
3. Preparations for Ice Storage Devices Debugging
1) 配合业主调试工作安排
1) Debugging arrangement which assorts proprietors
调试前完成所有蓄冰设备安装及验收工作,积极参加相应业主、监理及机电总包单位和厂商成立的联合调试工作小组工作,组织工程技术人员按时参加调试准备会议,按计划和审定详细调试步骤和操作程序,做出具体的调试安全防范措施,并由我公司进行蓄冰设备技术和责任澄清及协调工作。
Complete all the installment of ice storage devices and acceptance work; take part in the work by the united debugging team which is set up by relevant proprietors, supervisors, electromechanical general address contractors and manufacturers actively; organize engineering technical personnel to attend the debugging conference on schedule; work out specific debugging safety alarm measures according to the planned and audited detailed debugging steps and operation program; the technologies, responsibility declaration and coordination of ice storage device should be carried out by our company.
2012.12.1