招标答疑文件翻译-中英对照
蓄冰盘管外形-附后
3. Appearance of ice storage coil pipe - attached
2、 产品执行标准
4. Executive standard of products
1)、 设计、制造、检验标准(ASME认证)
1). Design, manufacturing, and testing specification (ASME certification)
益美高公司取得了ASME认证,其设计、制造、检验等均遵从ASME认证标准。益美高蓄冰设备的详细设计、制造检验标准见“蓄冰设备设设计、制造、检验、试验执行标准”。
Evapco Company has obtained the certification of ASME, the designs, manufacturing and testing, etc. comply with the standard of ASME certification. The detailed design and manufacturing standard of ice storage equipment of Evapco see “designs, manufacturing and inspection and executive standard of ice storage equipment”.
2)、 蓄冰设备材料检验、试验标准
2). materials inspection and testing standard of ice storage equipment
盘管原材料为美国标准的16号条形钢板,标号:ASTMA505。连箱材料标号: ASTMA36。
The raw materials of coil pipe applies the No. 16 steel plate of Unite States Standard, label: ASTMA505. Material label of connected case: ASTMA36
国标GB/T5213-2001, 08AL级。
National Standard GB/T5213-2001, 08AL grade
ASME认证标准。
ASME certificate standard
3)、 产品设计标准
3). Design standard of the product
ARI (美国空调制冷协会) 的 900标准;
The 900 standard of Air-conditioning and Refrigeration Institute (ARI)
ARI 的Guideline T准则,即美国蓄冰空调设计准则;
The Guideline T principle of ARI, i.e., the design principle of ice storage air-conditioner in America
GB9237-88 制冷设备通用技术规范
GB9237-88 General technical code for refrigerating plants
JB6917-1988 制冷装置用压力容器
JB6917-1988Pressure vessel for refrigerant equipment
4)、 制造、检验、试验标准
4). Standard of manufacturing, inspection and test
ISO9001:2000质量管理体系认证
ISO9001 : 2000 quality management system certification
Evapco公司已获得ISO9001:2000质量管理体系认证,认证书编号为US-3934,项目编号为011072 。
Evapco Company has obtained the ISO9001:2000 quality management system certification with the certificate No. US-3934 and project No. 011072.
原材料标准
Standard of origin material
盘管原材料为美国标准的16号条形钢板,标号:ASTMA505。连箱材料标号: ASTMA36。
国标GB/T5213-2001, 08AL级。
The raw materials of coil pipe apply No. 16 steel plate of Unite States Standard, label: ASTMA505. Material label of connected case: ASTMA36.
National Standard GB/T5213-2001, 08AL grade
焊接标准
Welding standard
焊接制造标准严格符合Evapco公司工厂的厂标,并获得ASME认证及ISO9001:2000质量管理体系认证。
The welding manufacturing standard shall strictly comply with the factory standard of Evapco Company and obtain the ASME certification and the ISO9001:2000 quality management system certification.
镀锌标准
Galvanization standard
盘管的镀锌标准性严格符合美国ASTMA123-89a标准。
The galvanization standard of coils shall strictly comply with the ASTMA123-89a standard in America.
GB/T13912-2002金属覆盖层、钢铁制件热浸镀锌层技术要求及实验方法。
GB/T13912-2002 Technical requirement and experimental method of metal coating layer and hot dip galvanized coatings on fabricated Iron and steel parts
探伤标准
Flaw detection standard
Evapco的探伤方式取得了ASTM-E309的认证。
The flaw detection method of Evapco has obtained the ASTM-E309 certification
气密标准
Air-tightness standard
严格执行ASME B31.5标准。
The ASME B31.5 standard shall be strictly implemented
检验标准
Inspection standard
检验标准严格符合Evapco公司工厂的厂标,并获得ASME及ISO9001:2000质量管理体系认证。
The implementation standard shall strictly comply with the factory strictly comply with the factory standard of Evapco Company and obtain the ASME certification and the ISO9001:2000 quality management system certification
包装标准
Packaging standard
包装方式严格符合Evapco公司质量规范系列,并获得ISO9001:2000质量管理体系认证。
The packaging method shall strictly comply with the quality specification series of Evapco Company and obtain the ISO9001:2000 quality management system certification
运输标准
Transportation standard
运输严格符合Evapco公司质量规范系列,并获得ISO9001:2000质量管理体系认证。
The transportation method shall strictly comply with the quality specification series of Evapco Company and obtain the ISO9001:2000 quality management system certification
调试标准
Commissioning standard
GB/T19412-2003 《蓄冷空调系统的测试和评价方法》
GB/T19412-2003 "testing and evaluation of cool storage air conditioning system”
Evapco调试标准严格遵循ARI 的 900标准。
The commissioning standard of Evapco Company shall strictly comply with the 900 standard of ARI
一、 管道冲洗
III. Pipeline cleaning
管道试压前,必须对管道进行冲洗,冲洗之前必须将设备前管道进行短路,以防脏物在设备内沉积,冲洗时先将盘管与干管连接处断开进行冲洗,后冲洗主干管,水从高端进入,以目测出水口水流清洁为合格,同时填写系统冲洗记录,送甲方、监理等有关人员会签。管道冲洗方案视现场情况另行制定。
Before pressure testing, it is necessary to clean the pipeline, and short out front pipeline of equipment before cleaning procedure in case of impurities deposited in equipment; clean the disconnected joints of the coil pipe and main pipeline, and then clean the main pipeline. The water is entered from higher position; water from outlet is clean for qualifying through the visual inspection; fill the system cleaning record at the same time. And submit to the relevant personnel of Party A and management etc. for countersign. The pipeline cleaning scheme shall be arranged according to the status on site.
蓄冰设备在工厂已进行冲洗,管道冲洗时蓄冰设备可不进行冲洗;机房内管道安装完毕后应按标准进行冲洗,冲洗效果需经过我单位同意后方可与冰槽内管道连接。
Ice storage equipments shall be cleaned in the factory. Ice storage equipments need not perform cleaning procedure in case of pipeline cleaning; the pipeline should be cleaned according to the relevant standard after being installed in the computer lab; the cleaning result shall be checked by our unit and join with the interior pipeline of ice tank after approval.
二、 压力试验
IV. Pressure test
1、 槽体闭水试验
1. Closed water test of tank body
蓄冰槽防水主要有两层:
The ice storage tank has two layers for waterproof:
第一层是防水砂浆层后的3mm厚JS防水涂料,本层防水施工完毕后应进行24小时的冰槽闭水试验。
The first layer is 3mm JS thick waterproof coating behind the waterproof mortar course, the waterproof operation of this layer shall perform 24 hours closed water test of ice tank body after completion.
第二层是保温层后的玻璃钢防水层,本层防水施工完毕后应进行24小时的冰槽闭水试验。
The second layer is glass fibre reinforced plastic waterproof layer after heat preservation, the waterproof operation of this layer shall perform 24 hours closed water test of ice tank body after completion.
2013.2.3